Gros Islet Fire Station is located in the North of the Island. This project commenced on the 1st of June 2001 and was completed on the 30th of March 2002. It was constructed by Rigo Dream Houses, with Architect Project Manager, Newel Lewis Broadbridge Associates (NLBA).

Dennery Fire Station is situated on the East Coast of the Island. This project commenced on the 1st of June 2001 and was completed on the 2nd of June 2002. It was constructed by Charles and Jules Construction Ltd, with Architect Project Manager Paul Hippolyte and Associates.

Vieux-Fort Police is situated in the East Coast of the Island. This project commenced on the 21st January 2002 and was completed on the 21st of January 2003. It was constructed by Dagcon Ltd, with Architect Project Manager Newel Lewis Broadbridge Associates (NLBA).

Anse La Raye Police Station is located in the West Coast of the Island. This project commenced on the 29th of June 2001 and was completed on the 20th March 2002. It was constructed by the National Contruction Ltd, with Architect Project Manager Leslie D. Mondesir.

Marchand Police Station is situated to the North East of the Island. This project commenced on the 25th of October 1999 and was completed on the 25th of November 2000. It was constructed by R&F Construction Ltd with Architect Project Manager Newel Lewis Broadbridge Associates (NLBA).

Marigot Police Station is situated to the North East of the island. This project commenced on the 25th of October 1999 and was completed on the 25th of November 2000. It was constructed by Caribbean Building Contractors with Architect Project Manager Leslie D. Mondesir.

Choiseul Police Station is situated in the South West of the Island. This project commenced on the 14th of March 2001 and was completed on the 30th of November 2001. It was constructed by A&A Construction Ltd with Architect Project Manager Total Design Associates/ Paul Hippoltye and Associates.

Canaries Police Station is situated to the West Coast of the Island. This project commenced on the 28th of November 2000 and was occupied on the 28th of October 2001. It was constructed by Peter Gustave Construction Ltd with Architect Project Manager Leslie D. Mondesir.

Laborie Police Station is situated to the South West of the Island. This project commenced on the 7th of June 2001 and was completed on the 28th of February 2002. It was constructed by Julius Boulogne with Architect Project Manager Total Design Associates.